September 6, 2023
With a new addition, Ridge Street Elementary School stands majestically, but getting it built was not an easy process. A recently issued report by the Office of the New York State Comptroller highlighted several issues related to the handling of bond construction change orders, which the Blind Brook School District must resolve before the project can close out.
Stories this photo appears in:
84% of B.B.’s construction change orders were not properly submitted to the state
District works to correct organizational errors that have been rooted in $50.7 million bond project
Change orders are back in the rhetoric at Blind Brook Schools, this time because the state has taken an interest in some red flags over the way they’ve been handled.
You must login to comment.